Solar EPC — sample project

Rajasthan Solar Phase II

Client
NTPC Renewable Energy Ltd
Contract value
₹85 Cr
Location
Jodhpur, Rajasthan
Project type
Solar EPC — 150 MW ground mount
Planned completion
30 Nov 2026
Forecast completion
18 Dec 2026
61%
Planned
70.3%
Actual
61%
Risk
Red

WBS tracker

CodeActivityUnitScopeExecutedPlanned %Actual %StatusResponsible
L3-01Land levelling & gradingCu.M4,20,0004,03,20096%96%On TrackSanjay Meena — Civil
L3-02Pile driving & MMS foundationNos18,40016,46893.5%89.5%DelayedR. Choudhary — Civil
L3-03Module mounting structure erectionMT3,1202,40291%77%DelayedVikas Sharma — Structural
L3-04PV module mountingNos2,72,0002,13,52076.5%78.5%On TrackPriya Nair — Execution
L3-05DC string cabling & terminationRMT1,86,0001,20,90074%65%DelayedA. Rathore — Electrical
L3-06Inverter & transformer installationNos462371.5%49.5%CriticalDeepak Joshi — Electrical
L3-07Internal roads & drainageRMT14,2008,23657%58%On TrackSanjay Meena — Civil
L3-08ICR & pooling substation worksMT64031054.5%48.5%DelayedDeepak Joshi — Electrical
L3-09Grid connection & bay extensionNos2052%21%CriticalM. Iyer — Grid
L3-10String testing & commissioningNos1,36036037.5%26.5%DelayedPriya Nair — Commissioning

BOQ summary

DescriptionUnitPlanned qtyActual qtyRateTotal valueVariance
PV module 545 Wp mono PERCNos2,72,0002,51,400₹11,800₹296.65 Cr-7.6%
Module mounting structure — galvanisedMT3,1202,740₹96,500₹26.44 Cr-12.2%
Foundation pile — drivenNos18,40017,960₹4,350₹7.81 Cr-2.4%
String inverter 250 kWNos4638₹11,20,000₹4.26 Cr-17.4%
DC cable 4 sq.mm solar gradeRMT1,86,0001,71,200₹68₹1.16 Cr-8%
Earthing & lightning protectionNos2,4002,180₹3,250₹0.71 Cr-9.2%
Internal road — WBMRMT14,20011,800₹2,850₹3.36 Cr-16.9%

Risk Radar preview

AI-Powered Risk Analysis — Available on Professional Plan
Low risk

Module supply on track

Container arrivals for blocks 1–6 are ahead of the mounting rate; 92% of DC capacity is on site.

Recommended mitigation: Hold the current mounting crew strength through the month.
Forecast impact: No impact on the PPA date.
Medium risk

Inverter delivery slipping

8 of 46 inverters are still in transit; block 7–9 AC commissioning depends on them.

Recommended mitigation: Escalate with the OEM and re-sequence commissioning to blocks 1–6 first.
Forecast impact: 12 days on AC commissioning if not recovered in 3 weeks.
Critical

Grid bay extension behind schedule

STU bay extension is 34 days behind, and evacuation readiness now drives the critical path, not module mounting.

Recommended mitigation: Weekly joint review with the STU; prepare an extension-of-time notice with the dated hindrance record.
Forecast impact: 18 days on synchronisation — currently the single largest exposure.

DPR snapshot

Date
24 Jun 2026
Overall progress
61%
Activities completed
2
Weather
Clear, 41°C
Workforce
486
Site photo — 24 Jun 2026

Module mounting crossed 6,200 modules for the day across blocks 3 and 4 — the best day this month. Pile driving in block 7 was held for four hours waiting on the rig shifting; logged as a hindrance. DC cabling in block 2 is ready for string testing from tomorrow.

WhatsApp alert

Plan-Sarthi Alerts
*Plan-Sarthi DPR Alert* Project: Rajasthan Solar Phase II Date: 24 Jun 2026 Today's Progress: 61% achieved vs 70.3% planned Activities Completed: 2 Activities Delayed: 7 Risk Status: Red Overall Completion: 61% Forecasted Completion: 18 Dec 2026 View Full Report: plansarthi.com — Plan-Sarthi by Sarthi Associates
18:00 ✓✓