| Code | Activity | Unit | Scope | Executed | Planned % | Actual % | Status | Responsible |
|---|---|---|---|---|---|---|---|---|
| L3-01 | Excavation & raft preparation | Cu.M | 1,86,000 | 1,78,560 | 96% | 96% | On Track | K. Subramanian — Civil |
| L3-02 | Raft foundation concreting | Cu.M | 42,800 | 38,306 | 93.5% | 89.5% | Delayed | K. Subramanian — Civil |
| L3-03 | Inner containment wall — lift 1 to 6 | Cu.M | 68,400 | 52,668 | 91% | 77% | Delayed | R. Balaji — Civil |
| L3-04 | Containment liner plate erection | MT | 4,260 | 3,344 | 76.5% | 78.5% | On Track | M. Prakash — Structural |
| L3-05 | Reactor building internal structures | Cu.M | 51,600 | 33,540 | 74% | 65% | Delayed | R. Balaji — Civil |
| L3-06 | Turbine hall foundations & pedestal | Cu.M | 38,200 | 18,909 | 71.5% | 49.5% | Critical | S. Anand — Civil |
| L3-07 | Cooling water intake structure | Cu.M | 74,800 | 43,384 | 57% | 58% | On Track | S. Anand — Civil |
| L3-08 | Embedded parts & anchor installation | Nos | 18,600 | 9,021 | 54.5% | 48.5% | Delayed | M. Prakash — Mechanical |
| L3-09 | Electrical & cable gallery works | RMT | 24,800 | 5,208 | 52% | 21% | Critical | V. Ganesh — Electrical |
| L3-10 | QA hold-point clearances & documentation | Nos | 1,840 | 488 | 37.5% | 26.5% | Delayed | T. Rajan — QA |
| Description | Unit | Planned qty | Actual qty | Rate | Total value | Variance |
|---|---|---|---|---|---|---|
| Concrete M50 — containment grade | Cu.M | 68,400 | 41,200 | ₹12,400 | ₹51.09 Cr | -39.8% |
| Reinforcement steel — containment | MT | 18,600 | 11,800 | ₹78,500 | ₹92.63 Cr | -36.6% |
| Liner plate — fabricated & erected | MT | 4,260 | 2,140 | ₹1,86,000 | ₹39.80 Cr | -49.8% |
| Embedded parts & anchors | Nos | 18,600 | 10,400 | ₹8,600 | ₹8.94 Cr | -44.1% |
| Raft concrete M40 | Cu.M | 42,800 | 42,800 | ₹9,800 | ₹41.94 Cr | 0% |
| Post-tensioning tendons | MT | 1,240 | 380 | ₹3,40,000 | ₹12.92 Cr | -69.4% |
| Cooling water intake — concrete | Cu.M | 74,800 | 38,600 | ₹8,900 | ₹34.35 Cr | -48.4% |
The raft is 100% complete with all QA hold points cleared and documentation signed at each stage.
Erection is at 2,140 MT of 4,260 MT with a rate of 118 MT a month against 145 MT required for the containment wall sequence.
34 QA hold points are awaiting joint inspection; concrete lifts 5 and 6 cannot proceed and the crew is partially idle.
Containment wall lift 4 concreting was completed with continuous pour over 19 hours; all mandatory tests recorded and witnessed. Lift 5 rebar tying is at 70%. Liner plate erection continued at El. +21.5 m. Hold-point clearance for the embedded parts in sector C is still pending with owner QA — logged.