HVAC — sample project

Mumbai Data Centre HVAC

Client
Tata Communications Ltd
Contract value
₹18 Cr
Location
Mumbai, Maharashtra
Project type
HVAC — Tier III data centre, 12 MW IT load
Planned completion
15 Oct 2026
Forecast completion
29 Oct 2026
70.3%
Planned
76.8%
Actual
70.3%
Risk
Red

WBS tracker

CodeActivityUnitScopeExecutedPlanned %Actual %StatusResponsible
L3-01Duct fabrication — shopSq.M34,60033,21696%96%On TrackF. Merchant — Fabrication
L3-02Duct erection & supportsSq.M34,60030,96793.5%89.5%DelayedF. Merchant — Execution
L3-03Chiller plant installationNos6591%77%DelayedG. Sawant — Mechanical
L3-04CRAH / AHU installationNos846676.5%78.5%On TrackG. Sawant — Mechanical
L3-05Chilled water pipingRMT4,1802,71774%65%DelayedD. Kadam — Piping
L3-06Insulation & claddingSq.M12,8006,33671.5%49.5%CriticalD. Kadam — Execution
L3-07BMS integration & cablingNos1,24071957%58%On TrackS. Fernandes — Controls
L3-08TAB & commissioningNos844154.5%48.5%DelayedS. Fernandes — Commissioning

BOQ summary

DescriptionUnitPlanned qtyActual qtyRateTotal valueVariance
GI ducting 24G — fabricatedSq.M34,60031,200₹1,240₹3.87 Cr-9.8%
Water-cooled chiller 800 TRNos64₹1,48,00,000₹5.92 Cr-33.3%
CRAH unit — precision coolingNos8462₹16,80,000₹10.42 Cr-26.2%
Chilled water piping MSRMT4,1803,640₹3,850₹1.40 Cr-12.9%
Nitrile insulation 25 mmSq.M12,80010,400₹890₹0.93 Cr-18.8%
BMS field devices & integrationNos1,240810₹14,200₹1.15 Cr-34.7%

Risk Radar preview

AI-Powered Risk Analysis — Available on Professional Plan
Low risk

Duct fabrication ahead of erection

The shop is holding a 4-week buffer over site erection, so no crew has waited on fabrication this month.

Recommended mitigation: Keep the fabrication shop on the current shift pattern.
Forecast impact: No impact; buffer protects the erection sequence.
Medium risk

Two chillers pending delivery

4 of 6 chillers are installed; the remaining two are due in 5 weeks, which compresses plant-room commissioning.

Recommended mitigation: Confirm the despatch date in writing and pre-complete all piping and electrical interfaces at the two vacant bases.
Forecast impact: 10–14 days on plant-room commissioning.
Critical

BMS integration behind, blocks TAB

BMS field device installation is at 65% with integration testing not started; TAB cannot begin without it and the client handover date is fixed.

Recommended mitigation: Add a dedicated controls team and start zone-wise TAB on completed halls rather than waiting for full BMS closure.
Forecast impact: 21 days on handover if integration is not accelerated now.

DPR snapshot

Date
24 Jun 2026
Overall progress
70.3%
Activities completed
2
Weather
Humid, 31°C
Workforce
168
Site photo — 24 Jun 2026

Hall 3 ducting reached 88% erected and pressure testing cleared on two branches. Chilled water piping welding continued in the plant room. BMS cabling in Hall 2 was held for six hours pending cable tray handover from the electrical contractor — logged as a hindrance.

WhatsApp alert

Plan-Sarthi Alerts
*Plan-Sarthi DPR Alert* Project: Mumbai Data Centre HVAC Date: 24 Jun 2026 Today's Progress: 70.3% achieved vs 76.8% planned Activities Completed: 2 Activities Delayed: 5 Risk Status: Red Overall Completion: 70.3% Forecasted Completion: 29 Oct 2026 View Full Report: plansarthi.com — Plan-Sarthi by Sarthi Associates
18:00 ✓✓