Wind EPC — sample project

Gujarat Wind Farm Cluster 3

Client
Adani Green Energy Ltd
Contract value
₹120 Cr
Location
Kutch, Gujarat
Project type
Wind EPC — 24 × 3.0 MW WTG
Planned completion
28 Feb 2027
Forecast completion
22 Mar 2027
61%
Planned
70.3%
Actual
61%
Risk
Red

WBS tracker

CodeActivityUnitScopeExecutedPlanned %Actual %StatusResponsible
L3-01Access road & crane platformRMT21,60020,73696%96%On TrackH. Patel — Civil
L3-02WTG foundation excavationCu.M34,80031,14693.5%89.5%DelayedH. Patel — Civil
L3-03Foundation concreting & curingCu.M12,9609,97991%77%DelayedNilesh Rana — Civil
L3-04Anchor cage & template settingNos241976.5%78.5%On TrackNilesh Rana — Civil
L3-05Tower section erectionNos966274%65%DelayedS. Bhatt — Erection
L3-06Nacelle installationNos241271.5%49.5%CriticalS. Bhatt — Erection
L3-07Blade assembly & hub fittingNos724257%58%On TrackK. Solanki — Erection
L3-08Internal cabling 33 kVRMT48,20023,37754.5%48.5%DelayedR. Trivedi — Electrical
L3-09Pooling substation & line stringingMT4108652%21%CriticalR. Trivedi — Electrical
L3-10Pre-commissioning & chargingNos24637.5%26.5%DelayedK. Solanki — Commissioning

BOQ summary

DescriptionUnitPlanned qtyActual qtyRateTotal valueVariance
Foundation concrete M35Cu.M12,96011,240₹7,450₹8.37 Cr-13.3%
Foundation reinforcement steelMT1,6801,512₹68,500₹10.36 Cr-10%
Tower section — 3 pieceNos9674₹48,50,000₹35.89 Cr-22.9%
Nacelle assembly 3.0 MWNos2418₹4,10,00,000₹73.80 Cr-25%
Blade set 68 mNos7254₹86,00,000₹46.44 Cr-25%
33 kV XLPE cableRMT48,20039,400₹1,480₹5.83 Cr-18.3%
Crane platform — GSB & compactionCu.M18,40016,900₹1,950₹3.30 Cr-8.2%

Risk Radar preview

AI-Powered Risk Analysis — Available on Professional Plan
Low risk

Foundation cycle stable

Foundation pours are averaging one WTG every 9 days against a plan of 10, with curing periods respected.

Recommended mitigation: Maintain two concurrent foundation crews.
Forecast impact: Two days ahead on the foundation package.
Medium risk

Blade consignment held at ghat section

Two blade sets are held pending police escort clearance on the ghat approach; the 600 T crane is on standby at WTG-14.

Recommended mitigation: Pre-clear escorts for the next three consignments and shift the crane to WTG-16 meanwhile.
Forecast impact: 6–8 days, plus idle crane cost of about ₹34 lakh.
Critical

Pooling substation charging at risk

Line stringing is 28 days behind and now controls first charging for the whole cluster.

Recommended mitigation: Add a second stringing gang and hold weekly joint reviews with the transmission agency.
Forecast impact: 22 days on cluster charging.

DPR snapshot

Date
24 Jun 2026
Overall progress
61%
Activities completed
2
Weather
Windy, 33°C
Workforce
214
Site photo — 24 Jun 2026

Nacelle for WTG-13 was lifted and bolted within the morning wind window. Blade assembly for WTG-12 stopped at 11:40 as wind speed crossed the erection limit — three hours idle, logged. 33 kV cable pulling continued between WTG-9 and the pooling station.

WhatsApp alert

Plan-Sarthi Alerts
*Plan-Sarthi DPR Alert* Project: Gujarat Wind Farm Cluster 3 Date: 24 Jun 2026 Today's Progress: 61% achieved vs 70.3% planned Activities Completed: 2 Activities Delayed: 7 Risk Status: Red Overall Completion: 61% Forecasted Completion: 22 Mar 2027 View Full Report: plansarthi.com — Plan-Sarthi by Sarthi Associates
18:00 ✓✓

Liked what you saw? Start managing your own Wind EPC project today.

Other sector demos