| Code | Activity | Unit | Scope | Executed | Planned % | Actual % | Status | Responsible |
|---|---|---|---|---|---|---|---|---|
| L3-01 | Access road & crane platform | RMT | 21,600 | 20,736 | 96% | 96% | On Track | H. Patel — Civil |
| L3-02 | WTG foundation excavation | Cu.M | 34,800 | 31,146 | 93.5% | 89.5% | Delayed | H. Patel — Civil |
| L3-03 | Foundation concreting & curing | Cu.M | 12,960 | 9,979 | 91% | 77% | Delayed | Nilesh Rana — Civil |
| L3-04 | Anchor cage & template setting | Nos | 24 | 19 | 76.5% | 78.5% | On Track | Nilesh Rana — Civil |
| L3-05 | Tower section erection | Nos | 96 | 62 | 74% | 65% | Delayed | S. Bhatt — Erection |
| L3-06 | Nacelle installation | Nos | 24 | 12 | 71.5% | 49.5% | Critical | S. Bhatt — Erection |
| L3-07 | Blade assembly & hub fitting | Nos | 72 | 42 | 57% | 58% | On Track | K. Solanki — Erection |
| L3-08 | Internal cabling 33 kV | RMT | 48,200 | 23,377 | 54.5% | 48.5% | Delayed | R. Trivedi — Electrical |
| L3-09 | Pooling substation & line stringing | MT | 410 | 86 | 52% | 21% | Critical | R. Trivedi — Electrical |
| L3-10 | Pre-commissioning & charging | Nos | 24 | 6 | 37.5% | 26.5% | Delayed | K. Solanki — Commissioning |
| Description | Unit | Planned qty | Actual qty | Rate | Total value | Variance |
|---|---|---|---|---|---|---|
| Foundation concrete M35 | Cu.M | 12,960 | 11,240 | ₹7,450 | ₹8.37 Cr | -13.3% |
| Foundation reinforcement steel | MT | 1,680 | 1,512 | ₹68,500 | ₹10.36 Cr | -10% |
| Tower section — 3 piece | Nos | 96 | 74 | ₹48,50,000 | ₹35.89 Cr | -22.9% |
| Nacelle assembly 3.0 MW | Nos | 24 | 18 | ₹4,10,00,000 | ₹73.80 Cr | -25% |
| Blade set 68 m | Nos | 72 | 54 | ₹86,00,000 | ₹46.44 Cr | -25% |
| 33 kV XLPE cable | RMT | 48,200 | 39,400 | ₹1,480 | ₹5.83 Cr | -18.3% |
| Crane platform — GSB & compaction | Cu.M | 18,400 | 16,900 | ₹1,950 | ₹3.30 Cr | -8.2% |
Foundation pours are averaging one WTG every 9 days against a plan of 10, with curing periods respected.
Two blade sets are held pending police escort clearance on the ghat approach; the 600 T crane is on standby at WTG-14.
Line stringing is 28 days behind and now controls first charging for the whole cluster.
Nacelle for WTG-13 was lifted and bolted within the morning wind window. Blade assembly for WTG-12 stopped at 11:40 as wind speed crossed the erection limit — three hours idle, logged. 33 kV cable pulling continued between WTG-9 and the pooling station.