Other Infrastructure — sample project

Delhi-Meerut Expressway Package 4

Client
National Highways Authority of India
Contract value
₹95 Cr
Location
Delhi – Uttar Pradesh border
Project type
Highway — 6 lane, 22 km package
Planned completion
31 Dec 2026
Forecast completion
24 Jan 2027
61%
Planned
70.3%
Actual
61%
Risk
Red

WBS tracker

CodeActivityUnitScopeExecutedPlanned %Actual %StatusResponsible
L3-01Clearing, grubbing & utility shiftingRMT22,00021,12096%96%On TrackR. Sehrawat — Civil
L3-02Earthwork in embankmentCu.M12,40,00011,09,80093.5%89.5%DelayedR. Sehrawat — Civil
L3-03Subgrade preparationCu.M1,86,0001,43,22091%77%DelayedM. Chauhan — Civil
L3-04Granular sub-base (GSB)Cu.M1,48,0001,16,18076.5%78.5%On TrackM. Chauhan — Civil
L3-05Wet mix macadam base courseCu.M1,21,00078,65074%65%DelayedS. Tomar — Pavement
L3-06DBM & bituminous concreteMT2,14,0001,05,93071.5%49.5%CriticalS. Tomar — Pavement
L3-07Culverts & minor bridgesNos462757%58%On TrackA. Kaushik — Structures
L3-08Major bridge — 4 span VUPNos3154.5%48.5%DelayedA. Kaushik — Structures
L3-09Drainage & protection worksRMT34,8007,30852%21%CriticalR. Sehrawat — Civil
L3-10Road furniture, marking & signageRMT22,0005,83037.5%26.5%DelayedP. Bisht — Execution

BOQ summary

DescriptionUnitPlanned qtyActual qtyRateTotal valueVariance
Earthwork in embankmentCu.M12,40,00010,84,000₹285₹30.89 Cr-12.6%
Granular sub-baseCu.M1,48,0001,21,400₹1,480₹17.97 Cr-18%
Wet mix macadamCu.M1,21,00092,600₹1,860₹17.22 Cr-23.5%
Dense bituminous macadamMT2,14,0001,48,200₹6,850₹101.52 Cr-30.7%
RCC culvertsNos4634₹18,40,000₹6.26 Cr-26.1%
VUP — 4 span structureNos31₹6,80,00,000₹6.80 Cr-66.7%
Drainage — lined drainRMT34,80024,600₹2,450₹6.03 Cr-29.3%

Risk Radar preview

AI-Powered Risk Analysis — Available on Professional Plan
Low risk

Earthwork nearly closed

Embankment is at 87% with borrow areas secured through the season; no stretch is waiting on earthwork.

Recommended mitigation: Release two excavator crews to the drainage front.
Forecast impact: No impact; earthwork will close ahead of the pavement window.
Medium risk

Utility shifting pending at 2 stretches

HT line shifting between chainage 11+400 and 12+900 is pending with the discom, holding GSB in that stretch.

Recommended mitigation: Follow the sanctioned estimate with the discom weekly and re-sequence the paving train to cleared stretches.
Forecast impact: 8–10 days on the pavement sequence for those chainages.
Critical

VUP structures behind schedule

Only 1 of 3 VUPs is complete; the remaining two control the corridor opening and the segment casting rate is below plan.

Recommended mitigation: Add a second casting yard and a launching girder shift, and review the milestone billing plan accordingly.
Forecast impact: 24 days on corridor opening.

DPR snapshot

Date
24 Jun 2026
Overall progress
61%
Activities completed
2
Weather
Clear, 36°C
Workforce
742
Site photo — 24 Jun 2026

Embankment closed 4,180 Cu.M across chainage 14+000 to 16+200. DBM paving ran two trains and laid 1,240 MT. GSB in the 11+400 to 12+900 stretch remained stopped for the ninth day pending HT line shifting — logged as a client-side hindrance with cost impact. Culvert at 15+600 completed and cured.

WhatsApp alert

Plan-Sarthi Alerts
*Plan-Sarthi DPR Alert* Project: Delhi-Meerut Expressway Package 4 Date: 24 Jun 2026 Today's Progress: 61% achieved vs 70.3% planned Activities Completed: 2 Activities Delayed: 7 Risk Status: Red Overall Completion: 61% Forecasted Completion: 24 Jan 2027 View Full Report: plansarthi.com — Plan-Sarthi by Sarthi Associates
18:00 ✓✓