| Code | Activity | Unit | Scope | Executed | Planned % | Actual % | Status | Responsible |
|---|---|---|---|---|---|---|---|---|
| L3-01 | Clearing, grubbing & utility shifting | RMT | 22,000 | 21,120 | 96% | 96% | On Track | R. Sehrawat — Civil |
| L3-02 | Earthwork in embankment | Cu.M | 12,40,000 | 11,09,800 | 93.5% | 89.5% | Delayed | R. Sehrawat — Civil |
| L3-03 | Subgrade preparation | Cu.M | 1,86,000 | 1,43,220 | 91% | 77% | Delayed | M. Chauhan — Civil |
| L3-04 | Granular sub-base (GSB) | Cu.M | 1,48,000 | 1,16,180 | 76.5% | 78.5% | On Track | M. Chauhan — Civil |
| L3-05 | Wet mix macadam base course | Cu.M | 1,21,000 | 78,650 | 74% | 65% | Delayed | S. Tomar — Pavement |
| L3-06 | DBM & bituminous concrete | MT | 2,14,000 | 1,05,930 | 71.5% | 49.5% | Critical | S. Tomar — Pavement |
| L3-07 | Culverts & minor bridges | Nos | 46 | 27 | 57% | 58% | On Track | A. Kaushik — Structures |
| L3-08 | Major bridge — 4 span VUP | Nos | 3 | 1 | 54.5% | 48.5% | Delayed | A. Kaushik — Structures |
| L3-09 | Drainage & protection works | RMT | 34,800 | 7,308 | 52% | 21% | Critical | R. Sehrawat — Civil |
| L3-10 | Road furniture, marking & signage | RMT | 22,000 | 5,830 | 37.5% | 26.5% | Delayed | P. Bisht — Execution |
| Description | Unit | Planned qty | Actual qty | Rate | Total value | Variance |
|---|---|---|---|---|---|---|
| Earthwork in embankment | Cu.M | 12,40,000 | 10,84,000 | ₹285 | ₹30.89 Cr | -12.6% |
| Granular sub-base | Cu.M | 1,48,000 | 1,21,400 | ₹1,480 | ₹17.97 Cr | -18% |
| Wet mix macadam | Cu.M | 1,21,000 | 92,600 | ₹1,860 | ₹17.22 Cr | -23.5% |
| Dense bituminous macadam | MT | 2,14,000 | 1,48,200 | ₹6,850 | ₹101.52 Cr | -30.7% |
| RCC culverts | Nos | 46 | 34 | ₹18,40,000 | ₹6.26 Cr | -26.1% |
| VUP — 4 span structure | Nos | 3 | 1 | ₹6,80,00,000 | ₹6.80 Cr | -66.7% |
| Drainage — lined drain | RMT | 34,800 | 24,600 | ₹2,450 | ₹6.03 Cr | -29.3% |
Embankment is at 87% with borrow areas secured through the season; no stretch is waiting on earthwork.
HT line shifting between chainage 11+400 and 12+900 is pending with the discom, holding GSB in that stretch.
Only 1 of 3 VUPs is complete; the remaining two control the corridor opening and the segment casting rate is below plan.
Embankment closed 4,180 Cu.M across chainage 14+000 to 16+200. DBM paving ran two trains and laid 1,240 MT. GSB in the 11+400 to 12+900 stretch remained stopped for the ninth day pending HT line shifting — logged as a client-side hindrance with cost impact. Culvert at 15+600 completed and cured.