| Code | Activity | Unit | Scope | Executed | Planned % | Actual % | Status | Responsible |
|---|---|---|---|---|---|---|---|---|
| L3-01 | Boiler structure erection | MT | 14,800 | 14,208 | 96% | 96% | On Track | R. Tiwari — Structural |
| L3-02 | Boiler pressure parts erection | MT | 9,600 | 8,592 | 93.5% | 89.5% | Delayed | R. Tiwari — Mechanical |
| L3-03 | ESP & ducting erection | MT | 6,200 | 4,774 | 91% | 77% | Delayed | A. Mishra — Mechanical |
| L3-04 | TG deck & turbine setting | MT | 3,400 | 2,669 | 76.5% | 78.5% | On Track | S. Dubey — Mechanical |
| L3-05 | Condenser installation | Nos | 1 | 1 | 74% | 65% | Delayed | S. Dubey — Mechanical |
| L3-06 | High pressure piping | Dia-Inch | 84,600 | 41,877 | 71.5% | 49.5% | Critical | P. Verma — Piping |
| L3-07 | Coal handling plant — conveyors | MT | 5,400 | 3,132 | 57% | 58% | On Track | K. Yadav — Mechanical |
| L3-08 | Ash handling & water systems | MT | 2,800 | 1,358 | 54.5% | 48.5% | Delayed | K. Yadav — Mechanical |
| L3-09 | Switchyard & electrical erection | MT | 1,900 | 399 | 52% | 21% | Critical | N. Gupta — Electrical |
| L3-10 | Hydro test, boiler light-up & synchronisation | Nos | 1 | 0 | 37.5% | 26.5% | Delayed | S. Dubey — Commissioning |
| Description | Unit | Planned qty | Actual qty | Rate | Total value | Variance |
|---|---|---|---|---|---|---|
| Boiler structural steel | MT | 14,800 | 12,640 | ₹96,500 | ₹121.98 Cr | -14.6% |
| Pressure parts — erection | MT | 9,600 | 6,820 | ₹1,48,000 | ₹100.94 Cr | -29% |
| High pressure piping — welding | Dia-Inch | 84,600 | 58,400 | ₹4,200 | ₹24.53 Cr | -31% |
| Turbine generator — setting & alignment | MT | 3,400 | 2,180 | ₹2,10,000 | ₹45.78 Cr | -35.9% |
| ESP & flue ducting | MT | 6,200 | 4,960 | ₹88,000 | ₹43.65 Cr | -20% |
| Coal conveyor structures & idlers | MT | 5,400 | 3,240 | ₹79,500 | ₹25.76 Cr | -40% |
| Switchyard structures & equipment | MT | 1,900 | 980 | ₹1,18,000 | ₹11.56 Cr | -48.4% |
Structural erection is averaging 420 MT a month against a plan of 400, keeping pressure parts unblocked.
58,400 of 84,600 Dia-Inch complete; the current rate leaves the balance about 5 weeks short of the hydro test window.
CHP conveyor erection is at 60% with civil handover still pending on junction towers 4 and 5, and CHP now controls trial run readiness.
Pressure parts erection closed 96 MT across the second pass and economiser. HP piping welding achieved 214 Dia-Inch against a target of 280 — two welders were diverted to a repair joint. TG deck grouting completed. Night shift progressed ESP internals; 22 workers idled for five hours awaiting a crane in the CHP area.